| HEAVY ENGINEERING PROJECTS | |||
A02 Südautobahn - Bridge constr. A6 to A10 and G22 |
pdf |
2014 | |
| Client: ASFINAG Service GmbH | |||
| Performance: Reconditioning concept and structural reanalysis | |||
| L704 Gatschberggraben-Bridge, reconditioning |
pdf |
2013 - 2014 | approx. € 1 mio excl. VAT |
| Client: Amt der Steiermärkischen Landesregierung | |||
| Performance: Reconditioning concept, structural reanalysis, tender and detailed design | |||
| L615 Saggau-Bridge, general overhaul and widening |
pdf |
2013 - 2014 | approx. € 600.000 excl. VAT |
| Client: Amt der Steiermärkischen Landesregierung | |||
| Performance: general design, documents for the water legislation procedure, tender and detailed design | |||
| S35 and S06 - Bridge constr., bridge evaluation |
pdf |
2013 | |
| Client: VA TECH WABAG GmbH | |||
| Performance: Bridge evaluation incl. structural reanalysis and reconditioning concept | |||
| General overhaul of the Waltenbach-bridge |
pdf |
Mayi 12 - Juni 2013 | approx. € 1,4 mio. excl. VAT |
| Client: ASFINAG Baumanagement GmbH | |||
| Performance: general design and detailed design | |||
| S36 Murtal-motorway - Main check of the bridge constr. |
pdf |
2011 - Oct. 2013 | |
| Client: ASFINAG Service GmbH Abteilung | |||
| Performance: Report and appraisal of the condition of the | |||
| construction | |||
| Feldaisttal-bridge in Freistadt Nord | pdf |
2012 - 2013 | approx. € 15 mio excl. VAT |
| Client: ARGE Ingenieurbau S10 BL 4.2 | |||
| Peformance: general design and detailed design | |||
| 2 railway bridges across the river Drava in Villach |
pdf |
2010 - 2012 | € 5,6 mio excl. VAT |
| Client: ÖBB Infrastruktur AG | |||
| Performance: general design and detailed design | |||
| Bridge overhaul - Kainach-bridge G63C |
pdf |
March 12 - Sept. 12 | |
| Client: Land Steiermark | |||
| Peformance: general design and detailed design | |||
| Forecourt of the former police station in Bad Radkersburg |
pdf |
Aug. 11 - Aug. 12 | |
| Client: Stadtgemeinde Bad Radkersburg | |||
| Performance: structural analysis, execution design | |||
| AST Salzburg Süd - overcrossing A10, triple-webbed T-beam | pdf |
2008 - 2011 | |
| Client: ASFINAG Baumanagement GmbH | |||
| Performance: general design and detailed design | |||
| L40 general refurbishment, A10 Tauernautobahn |
pdf |
March 2007 - June 2011 | |
| Client: ASFINAG Autobahn Service GmbH Süd | |||
| Performance: check-up of the statical design of the bracing | |||
| construction | |||
| Digestion tank Shiraz, new construction of 3 cylindrical tanks |
pdf |
since 2010 | not known |
| Client: VA TECH WABAG GmbH | |||
| Performance: construction design, structural analysis and | |||
| execution design | |||
| Wildbrücke, new construction of a road bridge |
pdf |
Febr. 2007 - 2010 | |
| Client: Stadtgemeinde Völkermarkt | |||
| Performance: general design and detailed design in cooperation with the office Zimmermann | |||
| Bikeway - bridge Bregenz - Hard | pdf |
2010 | approx.€ 1,45 mio excl. VAT |
| Client: Gemeinde Hard - Stadt Bregenz | |||
| Performance: complete design project | |||
| First prize - competition for the realisation | |||
| Power plant Almbach, new constr.of a hydroelectr. power plant | pdf |
July 09 - April 10 | € 3,45 mio excl. VAT |
| Client: Ingenieurbüro Eisner ZT GmbH | |||
| Performance: structural preliminary design, detailed structural analysis, formwork and reinforcement design | |||
| Temporary pedestrian bridge in Leibnitz across a railway track |
pdf |
March 2009 - April 2010 | |
| Client: ÖBB - Infrastruktur Bau AG | |||
| Performance: general project | |||
| A02 Süd Autobahn,
main bridge-evaluation |
pdf |
2009 | |
| Client: ASFINAG Service GmbH Süd | |||
| Performance: check-up and appraisal of the bridge construction | |||
| A09 Pyhrn Autobahn,
main bridge-evaluation |
pdf |
2009 | |
| Client: ASFINAG Service GmbH Süd | |||
| Performance: check-up and appraisal of the bridge construction | |||
| Frontier-bridge in Bad Radkersburg, bridge refurbishment |
pdf |
2004 - Nov. 2009 | approx.€ 1,4 mio |
| Client: Amt der Steiermärkischen Landesregierung | |||
| Performance: general project and detailed design | |||
| LSW Unterwald TA D Ratsch, noise barrier | pdf |
June 2007 - Sept. 2008 | |
| Client: ASFINAG Autobahn Service GmbH Süd | |||
| Performance: general design and detailed design | |||
| G21 – Talübergang, general bridge refurbishment | pdf |
Oct. 04 - July 08 | approx.€ 3,0 mio excl. VAT |
| Client: Amt der Steiermärkischen Landesregierung | |||
| Performance: general project and detailed project | |||
| Tehran Sewarage, 6 digestion tanks | pdf |
Sept. 2005 - June 2007 | |
| Client: VA Tech WABAG GmbH | |||
| Performance: structural analysis and constuctive design | |||
| P06V Zirknitzgrabenbrücke, Autobahn-arch-bridge |
pdf |
Aug. 2002 - Jan. 2006 | € 5,10 mio excl. VAT |
| Client: Amt der Steiermärkischen Landesregierung | |||
| Performanse: Revision of the general project and detailed design | |||
| Cable bridge in Halbenrain, Pedestrian and bikeway bridge |
pdf |
Sept. 2004 - Dec. 005 | € 0,60 mio excl. VAT |
| Client: Amt der Steiermärkischen Landesregierung | |||
| Performance: general design and detailed design | |||
| P40V Packabschnitt Niessenbachbrücke, new constr.archbridge |
pdf |
Jan. 2001 - Febr. 2003 | € 5,85 mio excl. VAT |
| Client: Amt der Steiermärkischen Landesregierung | |||
| Performance: general design and detailed design | |||
| Ski-road-bridge Katschberg, timber bridge construction |
pdf |
1998 | |
| Client: Dipl. Ing. Fritz Kermer | |||
| Performance: structural analysis and execution design | |||
| Wastewater treatment plant Graz-Gössendorf,
digestion tank |
pdf |
1996 | € 1,00 mio excl. VAT |
| Client: Bauunternehmung Granit | |||
| Performance: structural analysis and execution design | |||