Residential building Stainz

Construction phase I

Client: Gemeinnützige Grazer Wohnungsgenossenschaft registered co-operative with limited liability

The 11,000m² housing estate consists of 7 properties, 4 of which are being built as semi-detached houses. The project is divided into two construction phases, whereby construction phase I has already been completed.

Period of performance: 2018 – 2021 (construction phase I)

Dimensions: 150m x 100m x 15m (L/ W/ H/)

Performance: Structural design of steel, timber and solid construction (brick & concrete construction), tender planning, execution planning

Bridge objects A09 Pyhrn motorway and A02 South motorway-Styria South

Repair concept with static recalculation

Client: ASFiNAG Bau Management GmbH

On the A09 motorway, in the AST Spielfeld area and north and south of the Plabutsch tunnel, as well as on the A02 motorway in the Pack section, several bridges are due for repair. Repair concepts, in some cases with static recalculation, were drawn up to serve as the basis for tender planning.

Period of performance: 2022 – 2023

Performance: Static recalculation, creation of repair concepts based on structural tests, material analyses and recalculation.

New construction of raab bridge

Client: Office of the Styrian Provincial Government

The former B065 bridge over the Raab had reached the end of its planned service life. The new bridge was built to improve the alignment of the road on the one hand and the flood discharge on the other. The new construction is a single-span tied-arch bridge in steel-concrete composite construction.

Period of performance: 2018 – 2020

Dimensions:
Span: 29.20m
Width: 14.50m
Arch span: 6.50m

Performance: Preliminary study, water and road law submission, tender planning, detailed project

Testing and inspection of retaining structures

Client: ASFiNAG Bau Management GmbH

Testing and inspection of numerous unanchored support structures on the A09, S06, S35 and S36 motorways in accordance with RVS 13.06.61

Period of performance: 2021

Performance: Structural tests and inspections in accordance with RVS 13.06.61

A09 INTU Tunnel Rottenmann

Hot dimensioning of the existing Rottenmann tunnel.

Client: ASFiNAG Bau Management GmbH

Calculations were carried out with and without consideration of concrete spalling, as well as taking into account structural fire protection.

Period of Performance: 2021

Performance: Hot dimensioning

Structural analysis Gramatneusiedl

The remodelling of Gramatneusiedl station includes a reception building, a passenger footbridge, station roofs and a technical building.

Client: ÖBB-Infrastruktur AG

Period of performance: 2022 – 2023

Dimensions: Passenger footbridge: 2m x 17m

Performance: Structural design review of the tender and detail project

Source of the illustration: © ÖBB / ZKPT / 3-D Schmiede

Surgery BE 4a (LKH 2020 B)

Test statics surgery BE 4a

Client: Steiermärkische Krankenanstalentgesellschaft m.b.H.

In the old building of the surgery complex, in construction phase 4a
due to functional improvements, some rooms in the east wing were
changed in their utilisation. The structural measures ranged from
from earthquake frames made of steel and reinforced concrete, masonry
grouting, ceiling reinforcements and a load test to determine the load-bearing capacity
to determine the load-bearing capacity of a slab beam ceiling.

Period of Performance: 2019 – 2022

Service: Structural testing, consultant activity

Hochsteiner bridges I + II

B64 Restoration

Client: Office of the Provincial Government of Styria, Department 16

The Hochsteiner bridges I + II, on the B64 – Rechberg Straße, are to be subjected to interim maintenance. The pavement, the waterproofing and the drainage will be renewed. The existing edge beams including railings are to be retained.
In order to improve durability and simplify future maintenance, the road future maintenance, roadway transition structures will be dispensed with, the objects will be converted into semi-integral supporting structures.

Performance: Tender design, detailed design

Favoritenstreet 183-185

Extension and reconstruction favoritenstreet 183-185

Client: architectural office Leopold ZT GmbH

Period of performance: 2021 – 2023

Dimensions: 70m x 40m x 20m (L/W/H)

Performance: Structural planning of steel construction, concrete construction, timber construction, plan of execution

Silo Hunhary

New construction silo facility Hungary – cement silo

Client: Gleitbau Salzburg GmbH

Period of performance: 2021-2022

Dimensions: 22m x 22m x 32m (L/W/H)

Service: Structural planning of steel construction, concrete construction, execution planning

 

Addition BG/BRG Weiz

Addition to the BG/BRG Weiz

Client: Architectural office Goltnik ZT GmbH

Period of performance: 2021-2022

Dimensions: 50m x 15m x 10m (L/W/H)

Performance: Structural planning of steel construction, concrete construction, execution planning

Leistungszeitraum: (Deutsch) 2021-2022

Postquadrat – Housing construction Alte Poststraße

New construction of two wooden residential buildings with partial basements with underground parking for PREMIUM Immobilien GmbH

Client: Praschl-Goodarzi Architects ZT-GmbH

Period of Performance: 2019-2021

Dimensions: 60m x 40m x 13m (L / W / H)

Service: Structural planning, concrete construction, timber construction, implementation planning, fire protectic

Pictures: Copyright PREMIUM Immobilien

SeneCura Dobl

Construction of a new care home for the SeneCura Kliniken und Heimebetriebsgesellschaft mbH

Client: M&R GU GmbH

Period of Performance: 2020

Dimensions: 100m x 75m x 11m (L / W / H)

Service: Structural planning, concrete construction, implementation planning

Pictures: Copyright architectural office Harich

Student residence Innsbruck

Reconstruction, extension and extension of a 17.5m high existing building in Maximilianstrasse in Innsbruck

Client: Wallner & Schemitsch civil engineers

Period of performance: 2019-2021

Dimensions: 30m x 36m x 17m (L/W/H)

Services: structural engineering steel construction, concrete construction, timber construction, implementation planning, fire protection

Historic glass house Graz

Refurbishment of the historic steel and glass construction of the palm house in the Graz Botanical Garden

Client: BIG – Bundesimmobiliengesellschaft

Period of performance: 2018-2021

Dimensions: 56m x 8.5m x 11m (L / W / H)

Services: structural engineering steel construction, concrete construction, timber construction, implementation planning, fire protection

New building Silicon Austria Labs (SAL) & DH (DataHouse) TU Graz

Client: Zinterl Architekten ZT GmbH

Constructor: BIG Bundesimmobiliengesellschaft m.b.H.

Period of performance: 2018-2021

Overall dimensions: approx. 180m x 35m
Max. Height: about 20m

Performance: Static constructive preliminary design, structural design
Calculation of quantities, tendering (LVs building master work)
Detailed static calculation of concrete construction
Execution planning concrete construction (formwork and reinforcement)
Reinforcement acceptance

SMART CITY MIDDLE (SCM) Office building AVL

Client: SOD Office Development GmbH

Overall dimensions: approx. 90m x 20m
Max. Height: about 25m

Performance: Detailed static calculation of concrete construction
Execution planning concrete construction (formwork and reinforcement)
Reinforcement acceptance

Leistungszeitraum: 2018-2021

SMART CITY MITTE (SCM) parking garage AVL

Client: AVL List GmbH

Period of performance: 2018-2021

Overall dimensions: approx. 80m x 30m
Max. Height: about 20m

Performance: Detailed static calculation of concrete construction
Execution planning concrete construction (formwork and reinforcement)
Reinforcement acceptance

Pinzcker Vienna

Extension of bulk loading including acceptance gutter and conversion of existing buildings

Client: Bioprodukte Pinczker GmbH

Dimensions: 30.75m x 6.45m x 16.20m (L/W/H)

Performance: general planning, structural planning, fire protection planning, implementation planning, site supervision, BauKG

Leistungszeitraum: 2019-laufend

Farina Mill

Demolition and rebuilding of the semolina loading facility

Client: GoodMills Austria GmbH Loading

Period of performance: 2017-2018

capacity: 936 t

Dimensions: 19.40mx 9.80mx 32.30m (L/ W/H)

Services: general planning, structural planning, fire protection planning, implementation planning, site supervision, BauKG

Flour silo Kyjov (Tschechien)

Client: GoodMills Cesko

Period of performance: 2019-2020

Storage capacity: approx. 1350 t

Dimensions of the silo building: 19.30mx 13.25mx 26.95m (L/ W/ H)

Service: Concept planning, costing, structural planning, static-constructive processing

General refurbishment Johann Puch Museum Graz

Client: Holding Graz / Municipal Services GmbH

Period of performance: 2019

Usable area: 3,570.00m²
Dimensions: 91.00mx 30.00mx 7.50m (L/ W/ H)

Information: holdings from 1912

Services: Inventory, general static calculation (steel and timber construction), elaboration of the renovation concept in coordination with the BDA, fire protection planning, rough cost estimate,

New construction of bio silo plant

Client: Gsellmann Immo GmbH

Period of performance: 2017-2018

Storage capacity: 11.000 T
Dimensions: 41,00m x 12,80m x 57,00m (L/ W/ H)

Performance: general design, structural analysis, fire prevention desgin, execution planning, building supervision, construction coordination for health and safety issues

FBZ Traunkirchen

Client: Graf-Holztechnik GmbH

Period of performance: 2015-2017

Performance: detailed structural analysis of the timber construction

andritz ag

Client: Kulmer Holz-Leimbau GesmbH

Period of performance: 2017

Performance: structural analysis facade

Flood Protection Measure Kainach – Civil Engineering Structures

Client: urban municipality of Voitsberg

Period of performance: 2016-2017

Performance: general design, tender design, detailed design

Quartier 7 Reinighaus Graz

Client: ENW Gemeinnützige Wohnungsgesellschaft m.b.H.

Period of performance: 2016-dato

Performance: structural analysis, fire prevention design

Kammerlokal Carinthia, Klagenfurt

Client: Edgar Hammerl Architektur ZT GmbH

Period of performance: 2017

Performance: structural analysis (general plannung competition 1st prize)

Conversion – Andritz AG paper factory Graz

Client: Kamper ZT KG

Period of performance: 2016-2017

Performance: fire prevention design, accompanying fire protection, fire protection certificate

General renovation school center Deutschfeistritz

Competition

Period of performance: 2016/04

Leistungszeitraum: (Deutsch) 2016/04

Favoritenstraße 183-185, Extension and rebuilding

Client: Fa. ATLAS IMPORT EXPORT Ges. m.b.H.
Performance: engineering assessment, structural analysis

Leistungszeitraum: 2015/10 - 2016/03

Cardiac Rehab Bad Ischl

Client: Sozialversicherungsanstalt der gewerblichen Wirtschaft
Performance: accompanying fire protection, fire protection certificate

Leistungszeitraum: 2015 - 2016

ARA Gössendorf Capacity expansion of the post-thickener

Client:Stadt Graz vertreten durch die Holding Graz Services Wasserwirtschaft
Performance: preliminary structural analysis, statically constructive treatment, etc.

Leistungszeitraum: 2015 - 2017

SKA RZ Bad Schallerbach, annex and alteration

Client: BMASK Sektion II – Sozialversicherung
Performance: survey report of the price acceptability

Leistungszeitraum: 2014/05 - 2014/09

Extension of the silo constr. Gsellmann

Client: Gsellmann Mischfuttererzeugung GmbH
Performance: feasibility study, structural and constructive preliminary design, structural analysis

Leistungszeitraum: 2015/03 - 2015/07

New constr. of an apartment building, Graz

Client: Ing. Michelatsch GmbH
Performance: structural analysis, execution design

Leistungszeitraum: 2015 - 2016

S37 Klagenfurter highway – Design of the engineering construction

Client: Asfinag Baumanagement GmbH
Performance: preliminary design, general design, tendering, detailed design

Leistungszeitraum: 2015 - 2017

Check of the structural analysis of the annex of the state hospital in Feldbach

Client: KIG Steiermärkische Krankenanstaltengesellschaft mbH
Performance: check of the structural analysis

Leistungszeitraum: 2014/07 - 2017/07

Pedestrian Bridge Wölzbach

Client: Rauter Fertigteilbau GmbH
Performance: preliminary design, detailed design

Leistungszeitraum: 2014

WIKI gym center Graz

Client: Österreichisches Kinderrettungswerk Landesverband Steiermark
Performance: fire control planning, planning coordination, etc.

Leistungszeitraum: 2014/06 - 2015/06

New construction of a complex of buildings with basement car park, Graz

Client: Millöckergasse 27 – Wohnbau GmbH
Performance: structural analysis, execution design

Leistungszeitraum: 2014/05 - 2015/02

Seniorenzentrum Lassing, new construction

Client: Gem. Wohn- u. Siedlungsgenossenschaft ennstal
Performance: controlling of the execution of the fire prevention measures, fire prevention survey

Leistungszeitraum: 2014 - 2015

Medcampus Graz, new construction

Client: BIG
Performance: controlling of the execution of the fire prevention measures, fire prevention survey

Leistungszeitraum: 2014 - 2017

WIKI gym center Graz, new construction

Client: Österreichisches Kinderrettungswerk
Performance: supporting structure design (concrete constr.)

Leistungszeitraum: 2014 - 2015

Thermal bath Bad Elster, new construction

Client: Graf Holztechnik GmbH
Performance: detailed structural analysis of the timber constr.

Leistungszeitraum: 2014

LISI house on Paolo pontoons, new construction

Client: Hasslacher Holztechnik GmbH
Performance: structural analysis (incl. floating stability analysis)

Leistungszeitraum: 2014/06 - 2014/10

Wheelset axle test bench-Institute of Lightweight design (TU Graz)

Client: Zengerer Planung GmbH
Performance: structural analysis and execution design of the test benches

Leistungszeitraum: 2014/05 - 2014/10

Observation platform Krkonose, new construction

Client: Graf Holztechnik GmbH
Performance: structural preliminary design

Leistungszeitraum: 2014/04

A02 Südautobahn – Bridge constr. A6 to A10 and G22

Client: ASFINAG Service GmbH
Performance: Reconditioning concept and structural reanalysis

Leistungszeitraum: 2014

Bypass-bridges across the Danube

Competition

Leistungszeitraum: 2014/04

Alteration of the train station in Frohnleiten

Client: ÖBB-Infrastruktur Bau AG
Performance: general design, structural check of the existing construction

Leistungszeitraum: 2014

Housing estate Theodor-Körner-Straße 145 u. 145A, Graz

Client: Ing. Michelatsch GmbH
Performance: structural analysis, execution design

Leistungszeitraum: 2014 - 2015

Refurbishment design of the LKH West

Client: Krankenanstalten Immobilienges. mbH
Performance: structural analysis, detailed design

Leistungszeitraum: 2013 - 2014

L704 Gatschberggraben-Bridge, reconditioning

Client: Amt der Steiermärkischen Landesregierung
Performance: Reconditioning concept, structural reanalysis, tender and detailed design

Leistungszeitraum: 2013 - 2014

L615 Saggau-Bridge, general overhaul and widening

Client: Amt der Steiermärkischen Landesregierung
Performance: general design, documents for the water legislation procedure, tender and detailed design

Leistungszeitraum: 2013 - 2014

S35 and S06 – Bridge constr., bridge evaluation

Client: VA TECH WABAG GmbH
Performance: Bridge evaluation incl. structural reanalysis and reconditioning concept

Leistungszeitraum: 2013

Housing estate Eggenberger Allee 33, new construction

Client: Eggenberger Allee 33 – Wohnbau GmbH
Performance: complete supporting structure design

Leistungszeitraum: 2013 - 2014

Housing estate Körösistraße (Graz), new construction

Client: Körösistraße 138 – Wohnbau GmbH & Co KG
Performance: complete supporting structure design

Leistungszeitraum: 2013 - 2014

Tunnel-objects A07, A08 and A09, evaluation of the constructional fire protection and the structural components

Client: ASFINAG Baumanagement GmbH
Performance: incl. package of measures and rough cost estimate

Leistungszeitraum: 2013

Tunnel-objects S01, evaluation of the constructional fire protection and the structural components

Client: ASFINAG
Performance: incl. package of measures and rough cost estimate

Leistungszeitraum: 2013

Grandi Molini, storage building annex

Client: Grandi Molini Handel GmbH
Performance: general design

Leistungszeitraum: 2013 - 2014

thermal bath Kärnten Therme Warmbad-Villach

Client: Kärnten Therme GmbH
Performance: check of the structural analysis

Leistungszeitraum: 2013/03 - 2014/05

City hotel Margaretengürtel

Client: Michaeler & Partner
Performance: structural analyses, formwork and reinforcement design

Leistungszeitraum: 2012/07 - 2012/11

Check static calculation tribune Stadium Klagenfurt

Client: Arbeitsgemeinschaft Euro 2008
Performance: check of the structural analyses, vibration analyses

Leistungszeitraum: 2012 - 2013

McDonalds house for children, new construction

Client: Viereck Architekten ZT – GmbH
Performance: controlling of the execution of the fire prevention measures, fire prevention survey

Leistungszeitraum: 2012 - 2014

General overhaul of the Waltenbach-bridge

Client: ASFINAG Baumanagement GmbH
Performance: general design and detailed design

Leistungszeitraum: (Deutsch) 2012/05 - 2013/06

Feldaisttal-bridge in Freistadt Nord

Client: ARGE Ingenieurbau S10 BL 4.2
Peformance: general design and detailed design

Leistungszeitraum: 2012 - 2013

Bridge overhaul – Kainach-bridge G63C

Client: Land Steiermark
Peformance: general design and detailed design

Leistungszeitraum: 2012/03 - 2012/09

Housing estate Rosenkranzgasse 7,9, 11 Graz, new costruction

Client: Ing. Michelatsch GmbH
Performance: complete supporting structure design

Leistungszeitraum: 2012 - 2013

Preservation of evidence “Südgürtel”

Client: Amt der Steiermärkischen Landesregierung
Performance: Preservation of evidence of adjacent constructions

Leistungszeitraum: 2012 - 2016

Grüngasse 25, New construction and refurbishment

Client: Synergie Grüngasse 25
Performance: structural analysis, formwork and reinforcement design

Leistungszeitraum: 2011/07 - 2013/01

Objekt Gaudeamus Velenje School Centre, Slovenia

Client: Oberressl & Kantz ZT-GmbH
Performance: statical calculation

Leistungszeitraum: 2011

Recalculation and strengthening Retirement home Seekirchen

Client: UNIQA Sachversicherung AG
Performance: check of the structural analysis

Leistungszeitraum: 2011 - 2012

S36 Murtal-motorway – Main check of the bridge constr.

Client: ASFINAG Service GmbH Abteilung
Performance: Report and appraisal of the condition of the
construction

Leistungszeitraum: 2011 - 2013/10

Forecourt of the former police station in Bad Radkersburg

Client: Stadtgemeinde Bad Radkersburg
Performance: structural analysis, execution design

Leistungszeitraum: 2011/08 - 2012/08

SKA RZ Bad Aussee, annex and alteration

Client: BMASK Sektion II und Abteilung II/A/3
Performance: survey report of the price acceptability

Leistungszeitraum: 2011

SKA RZ Bad Tatzmannsdorf, partial new construction and modification of a rehabilitation centre

Client: BMASK Sektion II und Abteilung II/A/3
Performance: survey report of the price acceptability

Leistungszeitraum: 2011

Silo-plant Pinczker Albener Hafen, annex of a silo plant

Client: Bioprodukte Pinczker GmbH
Performance: general design

Leistungszeitraum: 2011/04 - 2012/10

Hydroelectric power plant in Kammern

Client: 2G Wasserkraft GmbH
Performance: preliminary structural analysis, detailed structural analysis, etc.

Leistungszeitraum: 2011/03 - 2012/03

General refurbishment of the A02 object P44L „Haswendbrücke“

Client: ASFiNAG Baumanagement GmbH
Performance: general design, tender design, structural analysis

Leistungszeitraum: 2011 - 2013

Weinkellersiedlung Kleinoscheg, new construction of a housing estate

Client: KS – Kern & Sommersguter Bauoptimierung GmbH
Performance: design of a fire prevention concept

Leistungszeitraum: 2010 - 2011

BG/BRG St. Martin Villach, renovation and modification

Client: Bundesimmobiliengesellschaft m.b.H.
Performance: controlling of the execution of the fire prevention measures

Leistungszeitraum: 2010 - 2011/09

Pedagogic academy in Eggenberg, extension and modification

Client: Architekt Goltnik ZT GmbH
Performance: controlling of the execution of the fire prevention measures

Leistungszeitraum: 2010 - 2011

2 railway bridges across the river Drava in Villach

Client: ÖBB Infrastruktur AG
Performance: general design and detailed design

Leistungszeitraum: 2010 - 2012

Digestion tank Shiraz, new construction of 3 cylindrical tanks

Client: VA TECH WABAG GmbH
Performance: construction design, structural analysis and
execution design

Leistungszeitraum: 2010

Bikeway – bridge Bregenz – Hard

Client: Gemeinde Hard – Stadt Bregenz
Performance: complete design project
First prize – competition for the realisation

Leistungszeitraum: 2010

Supply centre LKH Graz, nine-storey building

Client: Krankenanstalten Immobilienges.mbH
Performance: check of the structural analysis

Leistungszeitraum: 2010 - 2014

Housing estate Petersgasse 87 u. Friedensgasse 3, 3a, 3b

Client: Ing. Michelatsch GmbH
Performance: complete supporting structure design

Leistungszeitraum: 2010 - 2011

SKA RZ St.Radegund, new construction of a rehabilitation centre

Client: BMASK Sektion II und Abteilung II/A/3
Performance: Gutachten der Preisangemessenheit

Leistungszeitraum: 2010

Silo-plant STAMAG in Vienna, annex of a barley silo plant

Client: STAMAG-Stadlauer Malzfabrik GesmbH
Performance: supporting structure design

Leistungszeitraum: 2010/07 - 2011/12

Silo construction -Kittel Mühle Plaika, new construction

Client: Anton Kittel Mühle Plaika GmbH
Performance: supporting structure design and design of explosion prevention

Leistungszeitraum: 2010/12 - 2011/06

Bikeway-bridge Bregenz – Hard

Client: Gemeinde Hard – Stadt Bregenz
Performance: complete design performance
First prize – competition for the realisation

Leistungszeitraum: 2010

Supply Centre LKH Graz

Client: Krankenanstalten Immobilienges. mbH
Performance: check of the structural analysis

Leistungszeitraum: 2010 - 2016

Digestion tank Shiraz

Client: VA TECH WABAG GmbH
Performance: construction design, structural analysis, execution design

Leistungszeitraum: 2010

Power plant Almbach, new constr.of a hydroelectr. power plant

Client: Ingenieurbüro Eisner ZT GmbH
Performance: structural preliminary design, detailed structural analysis, formwork and reinforcement design

Leistungszeitraum: 2009/07 - 2010/04

A02 Süd Autobahn, main bridge-evaluation

Client: ASFINAG Service GmbH Süd
Performance: check-up and appraisal of the bridge construction

Leistungszeitraum: 2009

A09 Pyhrn Autobahn, main bridge-evaluation

Client: ASFINAG Service GmbH Süd
Performance: check-up and appraisal of the bridge construction

Leistungszeitraum: 2009

Villa Hillinger, new construction

Client: Leo Hillinger Privatstiftung
Performance: supporting structure design

Leistungszeitraum: 2009

RCA – hall in Vienna, redevelopment of the roof construction

Client: ÖBB Immobilienmanagement GmbH
Performance: structural evaluation, redevelopment concept

Leistungszeitraum: 2009 - 2010

AST Salzburg Süd – overcrossing A10, triple-webbed T-beam

Client: ASFINAG Baumanagement GmbH
Performance: general design and detailed design

Leistungszeitraum: 2008 - 2011

Residential establishment in Lanzendorf for handicapped people

Client: Architekturwerkstatt Graz
Performance: supporting structure design, geotechn. report

Leistungszeitraum: 2008/02 - 2012

Inpark Eggenberg, seven-storey new construction of a hotel

Client: EG – CENTER Errichtung und Verwaltung G.m.b.H.
Performance: complete supporting structure design

Leistungszeitraum: 2008 - 2011

Residential establishment in Schwechat for handicapped people

Client: Architekturwerkstatt Graz
Performance: supporting structure design

Leistungszeitraum: 2008 - 2009

Avalanche protection tunnel Mitholz

Client: Technical University Graz
Performance: drafting of an epert’s report on failure reasons

Leistungszeitraum: 2008/11 - 2009/03

Clocktower Graz, redevelopment of the timber construction

Client: City Graz – property management
Performance: structural evaluation, redevelopment concept

Leistungszeitraum: 2008 - 2009

Real estate evaluation, Eggendorf – M Hofer KG

Client: Michael Hofer KG
Performance: Evaluation of the physical structure and the equipment of the real estate

Leistungszeitraum: 2008

Silo-plant STAMAG in Graz , new constr. of a grain silo plant

Client: BM Ing. Ewald Haider GmbH
Performance: supporting structure design and design of explosion prevention

Leistungszeitraum: 2008 - 2009

Schafler – flour mill, new constr. of a granary

Client: Schafler – Mühle Ges.m.b.H.
Performance: structural analysis and explosion prevention

Leistungszeitraum: 2008 - 2009

Carpenter’s workshop Kletzenbauer, extension-production hall

Client: Tischlerei Kletzenbauer GmbH & Co KG
Performance: general design

Leistungszeitraum: 2008 - 2009

A2 Südautobahn – feeder Mooskirchen – general refurbishment

Client: ASFiNAG Service Gesellschaft Süd
Performance: general design, tender design, structural analysis, etc.

Leistungszeitraum: 2008/03

A2 South autobahn – feeder Mooskirchen – Bridgeobjekt ZM8

Client: ASFiNAG Service Gesellschaft Süd
Performance: general design, tender design, detailed design

Leistungszeitraum: 2008/01 - 2008/09

Fire prevention design – Raiffaisenlandesbank

Client: Immobilienerwerbs- und Vermietungs-Gesellschaft mbH
Performance: supervision of the fire prevention concept, design of a fire prevention concept, etc.

Leistungszeitraum: 2008 - 2014

Murien – basement garage- Serfaus

Client: Gemeindeamt Serfaus
Performance: structural analysis of the new construction, execution design

Leistungszeitraum: 2007/12 - 2008

Elevated tank construction Ragnitz

Client: Dipl.Ing. Franz Riesel
Performance: construction design, structural analyses

Leistungszeitraum: 2007

L40 general refurbishment, A10 Tauernautobahn

Client: ASFINAG Autobahn Service GmbH Süd
Performance: check-up of the statical design of the bracing
construction

Leistungszeitraum: 2007/03 - 2011/06

Wildbrücke, new construction of a road bridge

Client: Stadtgemeinde Völkermarkt
Performance: general design and detailed design in cooperation with the office Zimmermann

Leistungszeitraum: 2007/02 - 2010

LSW Unterwald TA D Ratsch, noise barrier

Client: ASFINAG Autobahn Service GmbH Süd
Performance: general design and detailed design

Leistungszeitraum: 2007/06 - 2008/09

General restoration Rothenthurmbridge

Client: Amt der Steiermärkischen Landesregierung
Performance: general design, tender design, structural analysis, detailed design, etc.

Leistungszeitraum: 2007/03 - 2008/01

A2 Südautobahn-Packabschnitt object P14 acute- reconstruction

Client: ASFINAG Autobahn Service GmbH Süd
Performance: check of the existent construction, suggestion of a restoration

Leistungszeitraum: 2007/01 - 2008/03

A2 Südautobahn- restoration P6 general reconditioning

Client: ASFiNAG Service Gesellschaft Süd
Performance: general design, tender design, structural analysis

Leistungszeitraum: 2006/09 - 2007/07

Caritas – school centre, New construction in Graz

Client: more architecture Goltnik ZT – KEG
Performance: fire prevention design

Leistungszeitraum: 2006 - 2008

Hotel Stavanger in Norway, three-storey hotel

Client: Stavanger Touristforening
Peformance: complete supporting structure design

Leistungszeitraum: 2006 - 2007

Timber construction in the form of a soccer ball

Client: Haas Fertigbau Holzbauwerk GmbH & Co KG
Performance: constructional draft and structural analysis

Leistungszeitraum: 2006

P32V Scharasbach-bridge A2 Packabschnitt

Client: Amt d. Steiermärkischen Landesregierung
Performance: statical calculation-consistency check of the structural analysis

Leistungszeitraum: 2005/01 - 2006/07

Retirement home and center for mobile services

Client: Architekturwerkstätte Graz-Architekt Wolf
Performance: construction design, structural analysis

Leistungszeitraum: 2005/12 - 2007/04

Tehran Sewarage, 6 digestion tanks

Client: VA Tech WABAG GmbH
Performance: structural analysis and constuctive design

Leistungszeitraum: 2005/09 - 2007/06

ABM – Bruck a.d.Mur, modification and extension

Client: ASFINAG Service GmbH Süd
Performance: complete supporting structure design

Leistungszeitraum: 2005 - 2008

Housing estate Andritz, New constr. with 5 seperated blocks

Client: Schauersberg Immobilien
Performance: complete supporting structure design

Leistungszeitraum: 2005 - 2007

Office building ASFINAG, extension and addition of stories

Client: ASFINAG Service GmbH Süd
Performance: gesamte Tragwerksplanung

Leistungszeitraum: 2005 - 2006

Gym hall WIKU in Graz

Client: Bundesimmobiliengesellschaft m.b.H.
Performance: structural analysis, execution design

Leistungszeitraum: 2005/03 - 2006/11

G21 – Talübergang, general bridge refurbishment

Client: Amt der Steiermärkischen Landesregierung
Performance: general project and detailed project

Leistungszeitraum: 2004/10 - 2008/07

Graz-Messehalle 11, demounting, reconstruction and bracing

Client: MCG Graz e.gen.
Performance: complete design (incl. supporting structure)

Leistungszeitraum: 2004/12 - 2008/04

Cable bridge in Halbenrain, Pedestrian and bikeway bridge

Client: Amt der Steiermärkischen Landesregierung
Performance: general design and detailed design

Leistungszeitraum: 2004/09 - 2005/12

Pedestrian bridge Ulmgasse

Client: ÖBB-Infrastruktur Bau AG
Performance: general design, tender design, structural analysis, etc.

Leistungszeitraum: 2003/07 - 2004/07

Adaptation and Service Work – Pumping Station Rudersdorf

Client: Stadt Graz – Holding Graz
Performance: documentation and static control of the building, safety and health protection plan, etc.

Leistungszeitraum: 2003 - 2008

Exhibition hall 1 in Graz, hall constr with basement garage

Client: MCG Graz e.gen.
Performance: complete supporting structure design

Leistungszeitraum: 2003 - 2008

Constructional engineering center Graz-Inffeldgasse

Client: Technical University Graz
Performance: complete supporting structure design

Leistungszeitraum: 2003 - 2007

Observation tower St. Peter-Ottersbach, new constr.

Client: Marktgemeinde St.Peter/ Ottersbach
Performance: complete design (incl. supporting structure)

Leistungszeitraum: 2003/05 - 2004/03

Hofermühle-compound feed production plant, new construction

Client: Company M. Hofer KG.Mischfutterwerk
Performance: general design

Leistungszeitraum: 2003 - 2004

P06V Zirknitzgrabenbrücke, Autobahn-arch-bridge

Client: Amt der Steiermärkischen Landesregierung
Performanse: Revision of the general project and detailed design

Leistungszeitraum: 2002/08 - 2006/01

Exhibition hall in Freistadt, cantilever timber- cupola constr.

Client: WIEHAG Gesellschaft mbH
Performance: constructional design and structural analysis

Leistungszeitraum: 2002

Towing rope bridge Lucia, new construction

Client: Dipl. Ing. Karisch
Performance: Evaluation of the supporting structure design

Leistungszeitraum: 2002/12 - 2003/04

Restoration ice rink in Salzburg

Client: Graf Holztechnik GmbH
Performance: structural check and inspection report

Leistungszeitraum: 2002/02 - 2002/06

Hotel Urthaler in South Tyrol, timber plate-/slab-construction

Client: family Urthaler/ Seiseralm Italien
Performance: complete supporting structure design

Leistungszeitraum: 2001/07 - 2002/04

Pilgrimage church Frauenberg, rehabilitation of the roof constr.

Client: Construction department of the monastery Admont
Performance: complete supporting structure design

Leistungszeitraum: 2001

Ice rink in Linz, redevelopment concept

Client: SBL-Stadtbetriebe Linz GesmbH Bäder
Performance: complete design

Leistungszeitraum: 2001

P40V Packabschnitt Niessenbachbrücke, new constr.archbridge

Client: Amt der Steiermärkischen Landesregierung
Performance: general design and detailed design

Leistungszeitraum: 2001/01 - 2003/02

School Karl Morre, reinforced concrete- and massive timber constr.

Client: Hypo Steiermark
Performance: complete supporting structure design

Leistungszeitraum: 2000/06 - 2002/09

Ennsbridge Liezen

Client: Amt d. Stmk. Landesregierung
Performance: general design, tender design, structural analysis, etc.

Leistungszeitraum: 1999/04 - 1999/10

Innovation centre W.E.I.Z., three-storey passive house

Client: Weizer Energie- Innovationszentrum
Performance: complete supporting structure design

Leistungszeitraum: 1998/04 - 1999/06

Ski-road-bridge Katschberg, timber bridge construction

Client: Dipl. Ing. Fritz Kermer
Performance: structural analysis and execution design

Leistungszeitraum: 1998

Wewalka, new construction of a production plant

Client: Wewalka GesmbH Nfg. KG
Performance: general design

Leistungszeitraum: 1997/06 - 1999

Massivholz production hall in Kalwang, new construction

Client: Massivholz GesmbH in Kalwang (Stmk)
Performance: general design

Leistungszeitraum: 1997

Digestion tank of a waste water treatment plant in Graz

Client: Bauunternehmung Granit Gesellschaft m.b.H.
Performance: construction design, structural analysis, execution design

Leistungszeitraum: 1996

Wastewater treatment plant Graz-Gössendorf, digestion tank

Client: Bauunternehmung Granit
Performance: structural analysis and execution design

Leistungszeitraum: 1996

Hospital of the “Deutscher Orden” Friesach

Client: Deutscher Orden Friesach
Performance: construction design, execution design

Leistungszeitraum: 1994/06 - 1997/02