Projects in progress

McDonald´s Fohnsdorf

Client:
McDonald’s Austria GmbH

New construction of a two-storey McDonald’s branch in Fohnsdorf. The building will be constructed entirely of reinforced concrete. The foundations will be made conventionally in in-situ concrete. The rising walls will be constructed using prefabricated hollow wall elements. All ceiling systems will be constructed primarily using hollow core slabs and partly using precast slabs.

Period of performance:
2025

Dimensions:
36.5m x 14.5m x 9.0m (L / W / H)

Performance:
Structural design for reinforced concrete construction
Execution planning

Extension and conversion stations C1-C4

Client:
Steiermärkische Krankenanstaltengesellschaft m.b.H.

Extension and remodelling of wards C1-C4 on the site of the ‘LKH Graz II, Standort Süd’.
The existing building will be reduced to the shell and the load-bearing structures
will be significantly modified. The gross floor area of the conversion is approx. 5,200m².
The extension is limited to a small bay window with a gross floor area of approx. 60m².

Period of Performance:
2024 until ongoing

Dimensions:
110m x 15m x 20m (L/ W/ H)

Performance:
Structural design steel, timber and solid construction (brick & concrete construction)
Implementation planning

New lorry workshop

Client: Gsellmann Immo GmbH

Gsellmann Immo GmbH is realising the new construction of a modern truck workshop
modern lorry workshop. The new building is intended to make the maintenance and
and repair of the company’s own vehicles efficiently and sustainably.

A workshop building is planned that is specially tailored to the company’s operational requirements. In addition to a truck wash with osmosis system and high-pressure cleaning, the building also includes a workshop with two lanes for lorries. In addition
storage facilities, including a spare parts store, an oil store and a locksmith’s workshop are also planned.

Period of performance:
06/2024 to ongoing

Performance:
Overall planning and coordination
Static-constructive processing
Master builder tender incl. sub-trades
Participation in the awarding of contracts
ÖBA construction
BauKG
Fire protection

Extension and remodelling of Villach town hall

Client:
Architekten Titus Pernthaler ZT GmbH

The extension and conversion of the Villach ice rink is divided into two sub-projects (TP01 & TP02).
TP01 involves the conversion of the existing hall. In TP02, the extension of an approx. 60m long and 22m wide 3-storey spandrel structure is being built directly adjacent to the south façade of the existing building. Directly adjacent to the gusset structure, a new training and ice rink measuring approx. 2250m² is being built.

Period of performance:
Construction phase I: 2023-2024
Construction phase II: 2025-2026

Dimensions:
Construction phase I:
85m x 60m x 16m
Construction phase II:
Spandrel structure: 60m x 22m x 16m
Ice rink: 65m x 35m x 12m

Performance:
Structural design steel, timber and solid construction (brick & concrete construction),
Implementation planning, fire protection planning

A10 underground road inspection

Client: ASFiNAG Bau Management GmbH

The existing St. Andrä underground route on the A10 Tauern motorway is to be demolished and rebuilt. It is essentially a twin-tube tunnel in cut-and-cover construction.

Period of performance: 2024-2025

Dimensions:
Total length: 470m
Spans: 2x10m

Performance:
Static-constructive inspection

L621 Sulmbridge Aflenz

Client: Office of the Styrian Provincial Government

The existing Sulmbrücke Aflenz bridge is to be rebuilt due to its poor state of repair. In the course of the new bridge construction, the line of the L621 will be improved, which is why the new bridge will be located upstream of the existing bridge. To improve the flood discharge, the flow cross-section will be enlarged compared to the existing bridge. For reasons of durability and maintenance, the new bridge will be designed as an integral supporting structure.

Period of performance: 2024 – 2025

Dimensions:
Span: 22.40m + 28.70m + 22.40m = 73.50m
Width: 9.75m

Performance: Preliminary design, submission planning, tendering, detailed design

Fini’s Feinstes-Mühle – Installation of an organic line

In order to meet the high demands of “organic customers”, the new organic milling line must be installed 100% separately from the conventional existing lines, from the grain delivery to the finished product (on pallets or loaded in batches).
A combined organic mill for grinding wheat, rye and spelt will be built. A new flour silo in reinforced concrete sliding construction will be built. Grain reception and bulk loading will be integrated into the existing plant. Furthermore, a separate bagging plant will be built.

Period of performance: 09/2022 – ongoing
Start of construction planned: 1st quarter 2024

Performance:
Overall planning and coordination
Static-constructive processing
Award procedure
ÖBA construction
BauKG
Fire protection

Graz bus depot

Client: GRDR Architektur ZT GmbH

The aim of the project is to build a bus depot with the necessary infrastructure for a total of 91 buses with alternative drive systems (electric and H2). The project is to be realised in two phases, with the bus depot being operated by buses with conventional drive systems until final completion and beyond. As things stand at present, 4 buildings will be erected: Carport, workshop building (FFM), administration, public H2 filling station, as well as an underground car park for an expected 60 parking spaces.

Period of performance: 2023 – ongoing

Dimensions: 150m x 100m x 12m (L/ W/ H)

Performance:
Preliminary design, construction design, submission planning, implementation planning, participation in the tendering process, participation in the awarding of contracts, support during construction, participation in local construction supervision

 

Research project FFG Large water heat storage

Client: Austrian Research Promotion Agency mbH

This project is a research project “TESconcrete Multifunctional concrete materials and holistic conception of large heat storage tanks for Austria”.
The aim of the project is to develop a hot-water-tight, durable and economical high-performance concrete material and multifunctional precast concrete components (sealing function, thermal insulation function, load-bearing function) for use in new types of large heat storage tanks for representative Austrian hydrogeologies.

Period of performance: 2022 – 2025

Dimensions: Ø35m x 35m

Performance: Statics

Project participants:
AEE – Institute for Sustainable Technologies
MABA Fertigindustrie GmbH
Smart Minerals GmbH (consortium leader)
STT GmbH
TU-Graz – Institute for Soil Mechanics, Foundation Engineering and Numerical Geotechnics
Wörle Sparowitz Ingenieure Ziviltechniker GmbH

RGB Revitalisation of Graz Castle

Client: Expedit Studio for Architecture

In the course of the revitalisation, historical treasures are to be made accessible to the general public. This concerns the 3-pillar and 1-pillar halls, as well as the chapel in the Friedrich wing and the ground floor and basement area of the Rigistratur wing of Graz Castle.

Period of performance: 2023 – 2025

Dimensions: 100m x 100m x 20m (L/W/H)

Performance: Structural design of steel construction, concrete construction, renovation of historic quarry stone masonry, execution planning

Birkenstraße

Client: Gemeinnützige Grazer Wohnungsgenossenschaft registered co-operative with limited liability

The approx. 24,000m² housing estate consists of 9 properties, 8 of which are being built as semi-detached houses. The project is divided into two construction phases. In construction phase I, a basement with underground car park is planned.

Period of performance: 2022 – ongoing

Dimensions: 180m x 140m x 15m (L/W/H)

Performance: Structural design of steel, timber and solid construction (brick & concrete construction), tender planning, execution planning, fire protection supervision

Holleneggerstraße

Client: Gemeinnützige Grazer Wohnungsgenossenschaft registered co-operative with limited liability

The approx. 13,000m² housing estate consists of 7 properties, 5 of which are being built as semi-detached houses. The project will be divided into two construction phases. There are currently no plans for an underground car park.

Period of performance: 2022 – ongoing

Dimensions: 205m x 65m x 15m (L/W/H)

Performance: Structural design of steel, timber and solid construction (brick & concrete construction), tender planning, execution planning, fire protection supervision

AU 19 Return kitchen ramp

Client: Steiermärkische Krankenanstaltengesellschaft m.b.H.

In the project, a later extension in front of the historic building is to be demolished or dismantled for reasons of monument protection. In the course of the conversion, a new staircase is to be built and new openings created in the load-bearing walls.
For the construction of the staircase, existing capped ceilings and slab beam ceilings are to be removed. It is planned to compensate for the stiffness of the ceilings in the form of a circumferential grid and to transfer the additional loads to the floor with new reinforced concrete columns in the basement.
The planned openings in the load-bearing walls represent a weakening of the load-bearing structure with regard to the building’s rigidity against earthquakes.
The weakening of the building is compensated for by additional steel frames and additional wall discs.

Period of performance: 2021 – 2025

Dimensions: 90m x 62m x 16m

Performance: statics

BIO grain silo system

Client: Anton Kittel Mühle Plaika GmbH

New construction of a BIO silo plant in slipform construction
with 35 cells on a floor space of 518m² and a storage capacity of
storage capacity of 11.1 tonnes with the following additional components:
– Receiving and loading
– dryer
– Intermediate building

Period of performance: 06/21 – ongoing
Start of construction: CW 10/23

Dimensions: 37.00m x 14.00m x 55.00m

Performance: Overall planning and coordination
Structural design processing
Master builder tender incl. sub-trades
Participation in the awarding of contracts
ÖBA construction
BauKG
Fire protection

Special inspection of bridge bearings

Client: ASFiNAG Bau Management Gmbh

In the course of regular bridge inspections, bearing misalignments were recognised on some bridges on the S06 and S35. The bearing positions had to be checked and the expected displacements calculated. Based on this, instructions for action and measures were to be developed.

Period of performance: 2021 – 2026

Performance: Special inspection of bridge bearings in accordance with RVS 13.03.11

Organic compound feed Gsellmann

New construction of a organic compound feed

Client: Gsellmann Immo GmbH

New construction of a organic compound feed in steel construction on a floor space of 1.600m² and a storage capacity of 7.200 tons with the following objects:
• Truck reception raw material (pre-cleaned) with rear tipper
• cleaning tower – storage cells raw material (silo cells)
• staircase
• machine wing (production) on different levels, incl. social room
• truck loading (bulk loading) with weighbridge
• truck delivery for silo trucks (blowing lines)
• Storage hall and filling of bagged goods and big bags
• Transformer building

In addition, a tent hall with an area of 385m² was erected as well as 9 truck parking spaces.

Period of performance: 11/2020 – ongoing
06/2021 until 11/2022 (construction)

Dimensions: 45.00m x 42.00m x 38.00m

Performance: Overall planning and coordination; Structural engineering; Construction tendering incl. sub-trades; Participation in awarding ÖBA BauKG Fire protection.

Vitakorn biosilo plant

Extension of the bio-storage silo

Client: Vitakorn Organic Feed Ges.m.b.H.

Extension of the bio-storage silo in solid construction with 28 cells on a floor area of 650m² and a storage capacity of 10.1 tons with the following additional components:
– Installation of a steam boiler house in the existing building
– Extension by two rear and side tipper castings
– New construction of weighbridge
as well as new construction of a bio-centre with office space and staff accommodation”.

Period of performance: 2020 – ongoing

Dimensions:
Bio storage silo = 30.20m x 20.20m x 35.20m
Bio Centre = 20.00m x 13.15m x 12.30m

Performance: Overall planning and coordination
Structural engineering
Construction tendering incl. sub-trades
Participation in the awarding of contracts
ÖBA, BauKG, Fire protection

HENSEL military barracks (5F02)

New construction of large-scale military barracks in Villach

Client: Wetschko architectural office ZT GmbH

Extension of the Hensel military barracks in Villach and new construction of large-scale barracks including conversion work in four existing buildings.
On a total area of 19.7 ha, 19 new buildings will be constructed and four existing buildings will be converted. A wide variety of building uses are being planned, such as office and administration buildings, accommodation buildings, storage buildings, a gymnasium, workshop buildings, a parking deck, a garage building, a troop doctor’s office, as well as an energy supply building, and much more.

Period of performance: 2022 – 2028

Performance: Fire protection planning, accompanying fire protection control, final report

Test statics radiology

New radiology building on the Graz Regional Hospital campuS

Client: Styrian Hospitals GesmbH

Period of performance: 2021-2023

Dimensions: 90m x 65m x 30m (L/W/H)

Performance: Test statics structural

Housing construction Johann-Josef-Fux-Gasse

New construction of 4 above-ground properties with a total of 44 residential units including underground parking

Client: GGW Charitable Graz Housing Cooperative

Period of performance: 2020 – ongoing

Dimensions: 120m x 35m x 11m (L/W/H)

Performance: structural engineering solid construction, implementation planning, fire protection, tendering for master builders, planning and construction law

s7_kunstbauten

Expressway S7 East – Civil Engineering Structures (44 Major Bridge and Byway Constructions)

Client: Asfinag Baumanagement GmbH

Performance: preliminary design, documents for the water legislation procedure, documents for the nature conservation legislation procedure, general design, tender design, detailes project