New construction of a organic compound feed
Client: Gsellmann Immo GmbH
New construction of a organic compound feed in steel construction on a floor space of 1.600m² and a storage capacity of 7.200 tons with the following objects:
• Truck reception raw material (pre-cleaned) with rear tipper
• cleaning tower – storage cells raw material (silo cells)
• staircase
• machine wing (production) on different levels, incl. social room
• truck loading (bulk loading) with weighbridge
• truck delivery for silo trucks (blowing lines)
• Storage hall and filling of bagged goods and big bags
• Transformer building
In addition, a tent hall with an area of 385m² was erected as well as 9 truck parking spaces.
Period of performance: 11/2020 – ongoing
06/2021 until 11/2022 (construction)
Dimensions: 45.00m x 42.00m x 38.00m
Performance: Overall planning and coordination; Structural engineering; Construction tendering incl. sub-trades; Participation in awarding ÖBA BauKG Fire protection.